Wednesday, August 25, 2010

Gas line installed; cleanup underway


Work went quickly today. The 4-inch flexible gas line is in place. The holes are filled with gravel. At some point the gravel will be covered with blacktop.

Tuesday, August 24, 2010

Repairs to the Gas Line


The natural gas line that leads to both the Cathedral, Rectory, and School is being replaced. The original line was probably installed in the 1950s when the campus buildings were converted from coal to gas.

The gas company's line runs north and south along Boulder Avenue. Holy Family taps into that line behind a meter on Boulder between the church and school.

The work should take several days.

Thursday, July 29, 2010

Middle School carpet DONE! Plus, couches in the new Media Center.

The Middle School carpet is done.

The Middle School Computer Lab & Media Center welcomed three leather couches. Great things are happening at Holy Family Cathedral School.


Tuesday, July 27, 2010

Update: Middle School hallway carpet

The Middle School classrooms, now carpeted and trimmed, are full of the desks and chairs that lined the main hallway last week. The bulk of the carpet is laid but needs to be trimmed.

Thursday, July 22, 2010

Update: Middle School carpet

The carpet installers have begun work in the Middle School classrooms.